⑴ use hoisting equipment to hoist the water pump into the foundation pit, cushion the iron, put on the anchor bolts, adjust the water pump foundation floor elevation and the level, tighten the anchor bolts, review the elevation and level, and strive to ensure the same as the design requirements.
⑵ Anchor Bolts Installation requirements: Before installation should be the anchor bolts on grease and dirt carefully clear clean. The contact surface of bolt and washer, washer and pump base shall be flat, without burrs and miscellaneous chips. The fastening of the anchor bolts shall be carried out after the concrete reaches the specified strength of 75%, and when the nut is tightened, the bolt must expose the 1.5~5 of the nut.
⑶ local foot bolts in accordance with the requirements of tightening, immediately with cement mortar between the base and the gap between the filling and filling, and then using concrete to fill the space under the base to ensure the stability of the base base.
Related News
- How To Install The Copper Valve?
- What Are The Reasons For The Damage...
- Classification And Principle Of Sol...
- Pipe Valves Should Be Installed Wit...
- Installation Of Hydraulic Pump
- Pump Selection And Modelling Calcul...
- Technical Requirements For Submersi...
- Solenoid Valve Type And Function Ch...
- Solenoid Valve Type And Function Ch...
- Brief Discussion On Pump Fault And ...
- Technical Use Of Pipeline Pump
- Causes And Solutions Of Vibration A...
- Repair Method Of Safety Valve Seali...
- Pipe Valves Should Be Installed Wit...
- Failure Analysis And Elimination Me...
- What Are The Installation Tips For ...
- Common Material Working Temperature...
- The Characteristics And Range Of Va...
- Analysis Of Several Causes Of Valve...
- How Many Connection Types Of Valves?